Using lean manufacturing tools in materials supply management during the life cycle of a construction project

Introduction. When choosing the Engineering, Procurement, Construction (EPC) contract model, the life cycle of construction projects is managed by a specialized contractor organization. This form of construction project management is relatively new for Russian developers, and its successful implemen...

Full description

Saved in:
Bibliographic Details
Main Authors: L. A. Oparina, E. A. Barzygin, Ya. A. Gridneva, N. S. Kasyanenko
Format: Article
Language:English
Published: Moscow State University of Civil Engineering (MGSU) 2024-05-01
Series:Vestnik MGSU
Subjects:
Online Access:https://www.vestnikmgsu.ru/jour/article/view/274
Tags: Add Tag
No Tags, Be the first to tag this record!
_version_ 1841553467696480256
author L. A. Oparina
E. A. Barzygin
Ya. A. Gridneva
N. S. Kasyanenko
author_facet L. A. Oparina
E. A. Barzygin
Ya. A. Gridneva
N. S. Kasyanenko
author_sort L. A. Oparina
collection DOAJ
description Introduction. When choosing the Engineering, Procurement, Construction (EPC) contract model, the life cycle of construction projects is managed by a specialized contractor organization. This form of construction project management is relatively new for Russian developers, and its successful implementation depends on various organizational and technical solutions, in particular, logistics management. The research problem is related to the existing risks of organizing the supply of material and technical resources during the implementation of construction projects using the EPC model, which have a negative impact on the most important indicators of construction efficiency, such as timing and cost. The paper describes strategies for preventing risk events that occur when planning the supply of material and technical resources during the life cycle of construction projects (risks of price changes, risks of violation of contractual obligations, risks of changes in the quality of delivery, reputational risks and risks of significant changes in demand). The problems of risk mitigation using lean manufacturing tools were solved.Materials and methods. The methodology and standards of project management as applied to the processes of material and technical support of construction, as well as methods of calendar-network planning, methods of project content decomposition, methods of contract strategy of construction projects implementation and elements of the methodology of package-node method of construction were used.Results. The results of the research are described and recommendations are given for the practical use of the flexible project management tool known in international practice as Just In Time.Conclusions. A justification for the use of the proposed planning tool as an activity to reduce risks associated with the supply of materials and improve the efficiency of life cycle management of construction projects is presented.
format Article
id doaj-art-99f30b3ab11a4b6d8d8b6fd0bc860edd
institution Kabale University
issn 1997-0935
2304-6600
language English
publishDate 2024-05-01
publisher Moscow State University of Civil Engineering (MGSU)
record_format Article
series Vestnik MGSU
spelling doaj-art-99f30b3ab11a4b6d8d8b6fd0bc860edd2025-01-09T08:22:49ZengMoscow State University of Civil Engineering (MGSU)Vestnik MGSU1997-09352304-66002024-05-0119582683510.22227/1997-0935.2024.5.826-835126Using lean manufacturing tools in materials supply management during the life cycle of a construction projectL. A. Oparina0E. A. Barzygin1Ya. A. Gridneva2N. S. Kasyanenko3Ivanovo State Polytechnic University (IVSPU)Ivanovo State Polytechnic University (IVSPU)Ivanovo State Polytechnic University (IVSPU)Ivanovo State Polytechnic University (IVSPU)Introduction. When choosing the Engineering, Procurement, Construction (EPC) contract model, the life cycle of construction projects is managed by a specialized contractor organization. This form of construction project management is relatively new for Russian developers, and its successful implementation depends on various organizational and technical solutions, in particular, logistics management. The research problem is related to the existing risks of organizing the supply of material and technical resources during the implementation of construction projects using the EPC model, which have a negative impact on the most important indicators of construction efficiency, such as timing and cost. The paper describes strategies for preventing risk events that occur when planning the supply of material and technical resources during the life cycle of construction projects (risks of price changes, risks of violation of contractual obligations, risks of changes in the quality of delivery, reputational risks and risks of significant changes in demand). The problems of risk mitigation using lean manufacturing tools were solved.Materials and methods. The methodology and standards of project management as applied to the processes of material and technical support of construction, as well as methods of calendar-network planning, methods of project content decomposition, methods of contract strategy of construction projects implementation and elements of the methodology of package-node method of construction were used.Results. The results of the research are described and recommendations are given for the practical use of the flexible project management tool known in international practice as Just In Time.Conclusions. A justification for the use of the proposed planning tool as an activity to reduce risks associated with the supply of materials and improve the efficiency of life cycle management of construction projects is presented.https://www.vestnikmgsu.ru/jour/article/view/274construction project life cyclemulti-level planningcalendar-network planningpackage-node construction methodriskslean manufacturingproject managementconstruction
spellingShingle L. A. Oparina
E. A. Barzygin
Ya. A. Gridneva
N. S. Kasyanenko
Using lean manufacturing tools in materials supply management during the life cycle of a construction project
Vestnik MGSU
construction project life cycle
multi-level planning
calendar-network planning
package-node construction method
risks
lean manufacturing
project management
construction
title Using lean manufacturing tools in materials supply management during the life cycle of a construction project
title_full Using lean manufacturing tools in materials supply management during the life cycle of a construction project
title_fullStr Using lean manufacturing tools in materials supply management during the life cycle of a construction project
title_full_unstemmed Using lean manufacturing tools in materials supply management during the life cycle of a construction project
title_short Using lean manufacturing tools in materials supply management during the life cycle of a construction project
title_sort using lean manufacturing tools in materials supply management during the life cycle of a construction project
topic construction project life cycle
multi-level planning
calendar-network planning
package-node construction method
risks
lean manufacturing
project management
construction
url https://www.vestnikmgsu.ru/jour/article/view/274
work_keys_str_mv AT laoparina usingleanmanufacturingtoolsinmaterialssupplymanagementduringthelifecycleofaconstructionproject
AT eabarzygin usingleanmanufacturingtoolsinmaterialssupplymanagementduringthelifecycleofaconstructionproject
AT yaagridneva usingleanmanufacturingtoolsinmaterialssupplymanagementduringthelifecycleofaconstructionproject
AT nskasyanenko usingleanmanufacturingtoolsinmaterialssupplymanagementduringthelifecycleofaconstructionproject